Work Period Management controls when work centres are unavailable to the RedAnt scheduler. Use it to maintain weekly non-working periods, dated closures, overtime and temporary alternative patterns.
Confirm the work centre is active and enabled for scheduling. The New and Edit work centre lists show only active work centres included in the scheduler. Ask your administrator for the relevant maintenance access if an option is unavailable; opening this screen through Scheduler requires Scheduler maintenance access, and deletion and clearance functions check Work Centres maintenance access.
Agree the normal operating hours, breaks, weekend working and any planned closures before entering records.
From Work Centres, select Setup → Work Period Management.
You can also open it from Scheduler → Setup → Work Period Management.
Entries in the main grid block out non-working time. Do not enter the productive shift itself as a blocked period. For a work centre operating 08:00–17:00, enter the time before 08:00 and after 17:00, plus any breaks during the day.
| Field | How to use it |
|---|---|
| Day of Week | The weekday to which the period applies. |
| Work Centre | The resource whose availability you are maintaining. |
| Shift No. | Use 1 for the normal pattern. Numbers above 1 identify alternative patterns applied through Shift Patterns. |
| Status | Select the appropriate description for the period, such as a locally configured break or non-working status. |
| Start Time and Finish Time | The beginning and end of the non-working period. |
| Date | Use 01/01/1900 for a repeating weekly entry. A different date creates a dated non-working entry in the normal pattern. |
| Duplicate entry for Days | Adds the same entry to the following number of weekdays, including weekends if the count reaches them. |
The form contains an Efficiency % control, but it is hidden in the reviewed form layout. Do not rely on changing efficiency here to make a period available for scheduling.
Duplication follows calendar weekday order and wraps from Saturday to Sunday. Check the selected day before using it.
Assume a work centre operates Monday to Friday, 08:00–17:00, with a non-working lunch break from 12:30–13:00. Create these entries under shift 1, dated 01/01/1900, using suitable locally configured statuses.
| Day | Non-working start | Non-working finish |
|---|---|---|
| Monday to Friday | 00:00 | 08:00 |
| Monday to Friday | 12:30 | 13:00 |
| Monday to Friday | 17:00 | 23:59 |
| Saturday | 00:00 | 23:59 |
| Sunday | 00:00 | 23:59 |
Create each Monday entry with 4 duplicate days. Enter Saturday and Sunday separately, or create Saturday with 1 duplicate day.
In recurring patterns, the scheduler treats an end time of 23:59 as the end of the day. The form does not accept a finish time of 00:00, and a single entry cannot span midnight. Split an overnight non-working period into two entries, one for each day.
To change a period, select its row, select Edit, amend the details and save. Check the weekday, shift number and date as well as the times.
Select the delete button to choose between:
Use Item for a single correction. Check the selected work centre before using Work Centre deletion.
Copy always takes shift 1 from the source work centre. It replaces all existing main-grid entries for the destination work centre and destination shift number. Selecting a source row from another shift does not change this behaviour.
You can copy shift 1 to a higher shift number on the same work centre, then edit the copied periods to create an alternative pattern. RedAnt prevents copying shift 1 back onto shift 1 of the same work centre.
Copying does not copy the separate Holidays / Downtime, Overtime or dated Shift Patterns records.
Use Holidays / Downtime for bank holidays, shutdowns, planned maintenance and other dated closures.
| Required scope | Entry |
|---|---|
| One work centre | Select its Work Centre ID. |
| All work centres | Leave Work Centre, Exclude First and Exclude Last empty. |
| All except a range of work centres | Leave Work Centre empty and set Exclude First and Exclude Last to the first and last IDs in the excluded range. |
The exclusion fields describe a range of work centre IDs, not two separate exceptions. Check the ID ordering before using a range.
Leaving all three work centre fields empty applies the closure to every scheduled work centre.
Check the time portion as well as the date. In this panel, choosing an end date through the calendar sets its time to 23:59. Enter the actual start and end times for a partial-day closure.
Overtime makes part of an existing non-working period available.
For example, if the normal pattern blocks Saturday 00:00–23:59, an overtime entry for Saturday 08:00–12:00 releases that interval for scheduling.
Overtime must be contained within a work centre non-working period. Split the request into separate entries if it crosses midnight or crosses the boundary between separate blocked periods. Calendar date selection does not establish the intended overtime hours; check and enter both times.
Use this when the weekly availability changes for a defined date range.
A higher shift number must have valid main-grid entries before it is assigned. Avoid overlapping assignments for the same work centre.
Keep the assignment within the scheduler's loaded date range and check it after changing that range. The reviewed scheduler selects alternative-pattern assignments whose start and end dates both fall within its loading window.
Check closures and overtime within an alternative-pattern range carefully: applying the alternative pattern clears existing non-working blocks starting within that date range before loading the replacement pattern.
Select Setup → Shift Status to open Status Codes. Maintain the descriptions and colour values required by your local setup, then use the panel's save control to commit the changes.
Keep descriptions consistent so users can identify the purpose of an entry. Changing a status description does not turn a main-grid period into productive time.
Review upcoming availability whenever working hours change and before publishing a production plan.
The Holidays / Downtime, Overtime and Shift Patterns panels each include Clear Entries. Enter the retention period in days to remove expired records. Clearance uses the record's end date/time compared with today's date minus the entered number of days.
Clear Entries applies across all work centres in that panel's records. Choose the retention period carefully and follow your organisation's record-retention process before clearing history.
| Symptom | What to check |
|---|---|
| A work centre is missing from New or Edit | Confirm it is active and enabled for scheduling. |
| Jobs can be placed outside working hours | Check that nights, breaks and weekends are explicitly blocked, using shift 1 and 01/01/1900 for recurring entries. |
| Jobs cannot be placed during normal hours | Check whether productive hours were entered as blocked periods; also review closures and alternative patterns. |
| A weekly entry appears only once | Check that its Date is 01/01/1900. |
| A closure affects every work centre | Check whether Work Centre and both exclusion fields were left empty. |
| Overtime does not release time | Check the work centre, the exact date/time interval and containment within one blocked period. |
| An alternative pattern does not appear | Check its shift number, main-grid entries, date range and the scheduler loading window. |
| Copied entries have disappeared or changed | Copy replaces the entire destination shift and always uses source shift 1. |
| The screen reports that time cannot span midnight | Split the period at the day boundary; finish the first entry at 23:59 and start the next at 00:00. |
| Changes are not visible in the current schedule | Close and reopen or reload the scheduler, then inspect availability before rescheduling work. |