Complete finished production work accurately, update the job status, and ensure time, quantity, and stock records remain correct.
Navigation: Main Menu > Job Orders > Complete
Before completing any Job Order or Works Order, confirm the following:
If the quantity produced is lower than planned, return any unused allocated material to stock before completion to maintain accurate stock balances.
Enter the finished quantity and any scrap quantity, then complete the operator's booking in Data Collection.
When RedAnt asks whether the job is complete, select Yes only if no further production work is required.
If more parts were produced than required, follow the prompt to place the agreed surplus quantity into stock.
Complete the booking and verify that the Job Order status changes to Complete.
Locate and select the relevant Job Order. Confirm both the Job Order number and Works Order number before proceeding.
Use the Information / Job Inquiry view to review:
Check Material Allocated to confirm what has been issued to the job.
Choose Complete from the actions at the top of the Job Order screen.
Select one of the following options:
Provide the required completion information, including:
Return unused material according to your company's stock procedures.
Select Mark Job Complete at the bottom of the completion window and save or confirm the transaction.
After completion, confirm that:
Job statuses normally progress automatically as work is activated, printed, started, and booked off. Manual completion should primarily be used for controlled corrections or for jobs that have been physically completed but remain open in the system.
Do not mark a Job Order as Complete simply to remove it from reports. Always reconcile quantities, time bookings, and materials before closing the order.
Completing a Job Order does not replace any separate delivery, certification, quality control, or invoicing processes required by your business procedures.
Some RedAnt installations use the same number for both the Job Order and Works Order. Other installations allow multiple Job Orders to be grouped under a single Works Order.
The completion options available will depend on your company's RedAnt configuration.